www.birmingham.gov.uk Alpha project - Project product map

simon gray - 2012-12-20, 15:54:26

Back in late September 2012, as part of my work at Birmingham City Council, I instigated and led on a programme of incremental improvements to the council's website, blogging about the ideas and progress along the way, taking inspiration from Shropshire Council's Project WIP and the Government Digital Service work on www.gov.uk. The site on which I blogged has been taken down now, but I thought it worth reposting the more broad-reaching content from it here.

As part of the iterative and agile process we’ll be working under, I’ve put together the first draft of our project map, identifying the various ‘products’ which will need to be developed as we go along:

As the project progresses we’ll be colouring those red boxes yellow and green, and adding more boxes along the trees, and of course adding new boxes and branches as new products are identified.

#localgovdigital #localgov

[...]

Read the rest of www.birmingham.gov.uk Alpha project - Project product map.

www.birmingham.gov.uk Alpha project - Developing the sub-projects

simon gray - 2012-12-03, 18:05:21

Back in late September 2012, as part of my work at Birmingham City Council, I instigated and led on a programme of incremental improvements to the council's website, blogging about the ideas and progress along the way, taking inspiration from Shropshire Council's Project WIP and the Government Digital Service work on www.gov.uk. The site on which I blogged has been taken down now, but I thought it worth reposting the more broad-reaching content from it here.

In order to make this whole project manageable, we need to split it up into a number of (initially five) sub-projects, from which our agile / Scrum series of products will emerge.

The sub-projects can be broadly grouped into three categories – content strategy, infrastructure, and governance. So far we have these:

Information Architecture

This is how people will navigate through the site – not just by the menu structure, but also A-Z, related links, and search. It will be looking at how content fits into the six top levels, identifying where the possible points for confusion lay, and mitigating that possible confusion.

Content

Relating to Information Architecture, we need to perform a content audit of the existing site and determine what pages we will need on the new site – the first pass being to establish what each page will cover, with subsequent passes being to actually write the new content based on matching and amending existing content to bring it in line with new content guidelines – which also need to be [...]

Read the rest of www.birmingham.gov.uk Alpha project - Developing the sub-projects.

www.birmingham.gov.uk Alpha project - Project outline, scope, goals, and outcomes

simon gray - 2012-09-14, 15:43:58

Back in late September 2012, as part of my work at Birmingham City Council, I instigated and led on a programme of incremental improvements to the council's website, blogging about the ideas and progress along the way, taking inspiration from Shropshire Council's Project WIP and the Government Digital Service work on www.gov.uk. The site on which I blogged has been taken down now, but I thought it worth reposting the more broad-reaching content from it here. This is the first post, which outlined what the project was actually about:

The Alpha project, inspired by the same methodology the central Government Digital Service has used as it redevelops https://www.gov.uk/ and Shropshire council’s Project WIP (http://shropshire.gov.uk/projectwip/), was conceived in March / April 2012 as a separate website on which we can develop and trial innovative developments in how we deliver services on birmingham.gov.uk in the future. Permission to proceed with the project was granted in early May, with the purchase order for the web hosting necessary for the work being sent to Service Birmingham on 7 June, with Service Birmingham delivering the development environment hosting on 4 July. Much of the background and preparatory work has been carried out over the course of time since summer 2011, including at various GovCamps, and work-in-earnest started on 12 September 2012.

Alpha has been conceived and designed from the ground up to facilitate an agile, iterative development process, allowing full consultation to take place and feedback to be received from key stakeholders – [...]

Read the rest of www.birmingham.gov.uk Alpha project - Project outline, scope, goals, and outcomes.